← All case studies

Telecom & Data Centres · 2025

Internal wiring for a carrier POP migration in Bahrain

Banks, an airport and an airline in Bahrain

Internal wiring for a carrier POP migration in Bahrain — key figures
10 customer sites
1 migration project
Bahrain

When a carrier moves its network, every customer site has to move with it.

The challenge

A carrier was migrating its point of presence in Bahrain. Each connected customer, including banks and the airport, needed new internal wiring to the new POP before the cut-over date.

How NteK solved it

  • Installed internal wiring from each customer's equipment to the new POP
  • Tested every new link
  • Coordinated timing with the carrier and the site owners

The result

10 critical customer sites wired and ready for migration, completed as one coordinated programme.